Coriolis Inspection ServicesThird-party witness inspection · Colorado, USA
Independent · Third-party · Boulder, Colorado

Third-party witness inspection for the equipment you are buying

We attend factory acceptance tests and ITP hold points at the vendor's shop on behalf of owners, EPC contractors and inspection agencies. You get an experienced inspector on the test floor, a flash report the same day and a complete inspection report within 24 hours.

  • Compressors & turbomachinery
  • API 610 pumps
  • Coriolis & flow metering
  • Valves
  • Heat exchangers & vessels
  • Electrical & packages
Clients
  • ADNOC
  • NMDC Energy
  • Venture Global
  • Baker Hughes
  • Intertek
  • LRQA
  • TÜV India (TÜV NORD Group)
  • EBFI
Large Coriolis flow meter sensor on a calibration test stand during a witnessed Factory Acceptance Test in Boulder, Colorado
Witnessed FAT: Coriolis sensor on the calibration stand at Emerson Micro Motion, Boulder.
  • 10+ years vendor inspectionOil & gas, petrochemical and power projects
  • ASNT NDT Level IIPT, MT and UT (SNT-TC-1A)
  • Reports within 24 hoursFlash report the same day
  • Based in Boulder, COColorado vendor shops and nationwide

Our most frequent inspection sites

Colorado vendor shops and test laboratories we attend most often for owners, EPC contractors and inspection agencies. Each card links to an example assignment at that site, with the scope, the tests witnessed and the deliverables. The full list of vendor shops inspected over the past ten years is further down the page.

Compressor test bay at Sundyne, Arvada, with large-bore test loop piping, overhead cranes and a centrifugal compressor package on the test bed
Arvada, Colorado · Compressors & pumps · Repeat site

Sundyne, Arvada: compressor performance test witnessing

A frequent site for us, a short drive from Boulder. Latest campaign, October 2026: four-stage integrally geared compressor tested to API 617 and ASME PTC 10 Type 2 on CO2 and nitrogen, witnessed over repeated site days with daily flash reports.

  • API 617
  • PTC 10 Type 2
  • CO2 / N2
  • Integrally geared
  • Repeat site
See the site page →
Coriolis flow meter sensor on the calibration stand at the Emerson Micro Motion plant in Boulder
Boulder, Colorado · Flow metering

Coriolis flow meter FAT witnessing at Emerson Micro Motion

Independent witnessing of hydrotest, PMI, calibration, configuration and functional tests, X-ray review and ATEX verification for Micro Motion Coriolis meters before shipment.

  • Coriolis
  • Calibration
  • PMI
  • Hydrotest
  • ATEX / IECEx
Read the case study →
CEESI flow calibration laboratory in Nunn, Colorado, where a 30-inch ultrasonic gas flow meter calibration was witnessed
Nunn, Colorado · Flow metering · May 2026

Ultrasonic gas flow meter calibration witnessed at CEESI

ITP witness point for an offshore riser platform project: as-found and as-left air calibration of a 30-inch ultrasonic meter, six points with five repeats each, with the meter's calibration quality computed independently within 24 hours. The result was not good, and the contractor knew before shipment.

  • Ultrasonic
  • As-found / as-left
  • ITP witness
  • Sonic nozzles
  • 24 h evaluation
Read the case study →
Copper Chem-Rod grounding electrodes on a pallet during pre-shipment inspection at Lightning Eliminators & Consultants, Boulder
Boulder, Colorado · Electrical materials · Aug 2026

Pre-shipment inspection of lightning protection materials at LEC

Final inspection of 25 line items of lightning protection and grounding material for a gas plant project, on behalf of an international inspection agency: quantity and ID, dimensional checks, MTR/CoC review and Inspection Release Note.

  • Final inspection
  • Dimensional
  • MTR / CoC
  • IRN
  • TPI agency
Read the case study →

What a witness inspector does for you

When you buy a compressor, a pump, a flow meter or a vessel, the vendor tests it in their own shop against an Inspection and Test Plan (ITP). A third-party witness inspector, also called a Supplier (or Source) Quality Representative, SQR, or source inspector, is your representative at those tests. We confirm that each test is run per the approved procedure, that the readings meet the acceptance criteria, that the material certificates match the hardware, and that nothing ships with an open non-conformance.

Coriolis Inspection Services LLC works for the buyer side only: owners and operators, EPC contractors and inspection agencies that need a qualified inspector at a vendor in Colorado or elsewhere in the United States. We never represent the vendor whose equipment is being inspected.

What you receive

  • Attendance at every hold and witness point in the ITP or Notification of Inspection (NOI)
  • Same-day flash report after each activity
  • Inspection report within 24 hours with photos, test data and sign-offs
  • Non-conformance reports (NCR) and punch list, followed to closure
  • Review of MTCs, calibration certificates, NDT records and the final dossier (MRB)
  • Every witnessed test report signed off before we leave the shop: hydrotest, PMI, NDT, dimensional, performance and functional tests
  • Inspection Release Note when the equipment is ready to ship
H

Hold point

The vendor cannot proceed until we have witnessed and signed the step and a Release to Proceed (RTP) is given. "RTP on hold" means that release is withheld until an open issue is resolved. Typical: hydrostatic test, performance test, final inspection before packing.

W

Witness point

We are notified and attend; the vendor may proceed after the notice period if we waive. Typical: NDT, dimensional checks, coating thickness, functional tests.

R

Review point

We verify documents rather than hardware: material certificates, WPS/PQR, calibration certificates, test records and the manufacturer's data book.

Equipment we inspect and tests we witness

Scope drawn from more than ten years of vendor and third-party inspection. Each card lists the tests we most often witness for that equipment family and the standards they are run to.

Rotating equipment

Compressors & turbomachinery

Centrifugal, axial, integrally geared, oil-free screw and reciprocating (process and hyper) compressors, turboexpanders, fans and blowers.

  • Performance test (APT) at one or more speeds, including PTC 10 Type 2 tests on nitrogen or CO2
  • Mechanical running test (MRT) and unloaded run
  • String and uncoupled tests, overspeed, vibration
  • Rotor balance, dry gas seal and lube oil console checks
  • Casing hydrotest, internal and bearing dismantling inspection

API 617 · API 618 · API 672

Rotating equipment

Pumps & drivers

API 610 overhung, between-bearings and vertical pumps, high-pressure barrel pumps, fire-water packages, motors and gearboxes.

  • Performance (H-Q) and NPSH tests
  • Mechanical run, vibration and bearing temperature
  • Hydrostatic casing test at 1.5× design
  • API 682 seal plan verification, alignment and run-out
  • Motor electrical checks, coating DFT, preservation

API 610 · API 682 · NFPA 20

Measurement

Flow metering & instrumentation

Coriolis mass flow and density meters, wet gas and multiphase meters, ultrasonic and DP meters, pressure and temperature transmitters, fire and gas detectors.

  • Calibration against traceable reference meters
  • Meter factor, zero stability and density verification
  • Transmitter configuration, 4-20 mA / HART loop tests
  • Ex / IP nameplate and certificate verification
  • SIL certificate and proof-test interval review

AGA 9 · ISO 5167 · ATEX / IECEx

Pressure equipment

Valves & regulators

Control, isolation, ball and trunnion valves, pressure regulators and steam conditioning valves from major valve manufacturers.

  • Hydrostatic shell and seat leakage tests
  • Actuator stroke, positioner and feedback tests
  • Material traceability and PMI of pressure parts
  • Bore, flange face and coating checks
  • Marking, tagging and export packing

API 598 · API 6D · ASME B16.34

Static equipment

Heat exchangers, vessels & boilers

Shell-and-tube and plate heat exchangers, surface condensers, steam ejector vacuum systems, economizers, package boilers and tanks.

  • Shell and tube side hydrotest with hold time
  • Weld inspection: VT, PT, MT, UT and RT film review
  • Tube-to-tubesheet joint inspection
  • Dimensional survey against GA drawings
  • U-stamp data report, WPS/PQR and MTC review

ASME VIII · ASME IX · TEMA · HEI

Electrical & packages

Electrical equipment & skids

Power and distribution transformers, GIS and LV switchgear, circuit breakers, motors, generators, cranes and integrated skid packages.

  • Insulation resistance, ratio, winding resistance and loss tests
  • Dielectric withstand and partial discharge
  • Functional, interlock and I/O list verification
  • Control panel FAT and communication tests
  • Load tests, packing and shock indicators

IEC 60076 · IEC 62271 · IEC 60034

Test procedures

Factory Test Procedure (FTP) review

The FTP, also written as Functional or Final Test Procedure, is the vendor's written procedure for a shop test: exactly how the test is run and what counts as a pass. It is usually submitted to the client for approval before the FAT and referenced on the ITP or NOI, for example "Performance test per FTP-xxxx Rev 2". The approved FTP is the yardstick the witness inspector judges the test against, and its filled-in data sheets usually become the signed test report. Related documents include the Fire Test Procedure for fire-safe valves (API 607 / API 6FA) and the Field Test Procedure for tests at site.

What an FTP contains

  • Scope: equipment, tag and serial numbers, and which tests are covered
  • References: applicable standard, datasheet, PO and the ITP line it covers
  • Test setup: loop or bench diagram, instruments with range, accuracy and calibration
  • Step-by-step method: test points, speeds, flows or pressures, hold times, number of readings
  • Acceptance criteria: tolerances on head, flow, power, efficiency, vibration, temperature, leakage
  • Data sheets with signature blocks for vendor QC, inspector and client

What we check

  • The revision on the test floor is the approved revision listed in the NOI or document register
  • Test setup and instruments match the procedure, with valid calibration certificates
  • Every test point, run time and number of readings is performed as written
  • Results compared with the acceptance criteria, including corrections to rated conditions
  • Deviations from the procedure recorded, and raised as comments or NCRs where they affect acceptance
  • Data sheets completed and signed at the test

API 610 · API 617 · IEC 60076 · approved vendor procedure

Rotating equipment

Compressor performance test on nitrogen and CO2

A process compressor is rarely shop-tested on its real gas: a hydrocarbon or sour process gas cannot be run safely in an open test loop. Instead the performance test is run as an ASME PTC 10 Type 2 test on a substitute gas, and the results are converted to the specified conditions. To be valid, the test must keep the machine aerodynamically similar to its duty: matching flow coefficient, volume ratio across the stages and machine Mach number within the PTC 10 limits. Nitrogen (molecular weight 28) is inert and easy to handle, and is often also a real operating case on the datasheet, such as start-up or minimum operating speed. CO2 (molecular weight 44) is heavier, so it develops the head and volume ratio of a heavier process gas at a speed the test stand can reach. That is why a multi-stage compressor is often tested on both.

What we check

  • Test gas named in the approved test procedure and similitude calculation, with a gas analysis or purity certificate for each gas
  • Each test case (gas, speed, inlet conditions) matches the case agreed in the procedure and datasheet
  • Flow points from surge to stonewall, including the rated point, with the required stabilisation time and number of readings
  • Orifice plates, pressure and temperature transmitters and speed pickups calibrated, with certificates on file
  • Conversion from test gas to specified gas checked: head, flow and power compared with the API 617 and purchase specification tolerances
  • Vibration, bearing temperatures, seal and oil system readings logged throughout each run

Recent example

Sundyne, Arvada, Colorado, October 2026: performance test of a four-stage integrally geared vapour recovery compressor, witnessed on CO2 and on nitrogen to API 617 and ASME PTC 10 (Type 2), five flow points from surge to stonewall per run, with daily flash reports and photo records.

ASME PTC 10 (Type 2) · API 617 · approved test procedure and similitude calculation

Surveillance

In-process inspection (IP)

An in-process inspection is a visit during manufacturing, before the equipment is finished. Agencies and clients usually label visits by stage: PIM or kick-off meeting before work starts, IP (in-process) while the item is being made, and FI (final inspection) before shipment. On the ITP or NOI, IP lines are usually witness or surveillance points, and an assignment can simply be a periodic "IP visit". The purpose is to catch problems while they are still cheap to fix: a wrong material or a bad weld found in process is a repair; found at final inspection, it may already be hidden under machining, assembly or paint.

  • Material identification and heat number transfer as parts are cut or machined
  • Fit-up and welding: WPS / PQR, welder qualifications, weld visual
  • NDT and PMI as they are performed
  • Intermediate dimensional checks against drawings
  • Heat treatment charts and furnace records
  • Assembly checks: clearances, rotor balance, seal installation
  • Coating surface preparation before paint
  • Progress against the schedule, open NCRs and the next notification

Approved ITP · NOI · Material Requisition (MR) and PO requirements

Pressure testing

Hydrostatic & pressure test witnessing

A hydrostatic test proves that pressure equipment is strong and leak-tight before it ships. The vessel, piping spool, valve body, pump or compressor casing or heat exchanger is filled with water, vented of air and pressurised above its design pressure, typically 1.3 to 1.5 times design depending on the code, then held for a set time while it is checked for pressure drop, leaks and deformation. Where water cannot be used, a pneumatic test with air or nitrogen is run under stricter safety controls.

Why the buyer needs it witnessed

  • It is a mandatory hold point: the vendor cannot coat, insulate or ship until it is signed
  • It is the last practical chance to find weld or casting defects before the part is buried in a plant
  • An independent check that the test was run as approved, not as convenient
  • The signed certificate and chart are required in the dossier (MRB) for owner and jurisdiction acceptance

What we verify

  • Approved procedure, test pressure and hold time against code and datasheet
  • Gauge and recorder calibration certificates and suitable gauge range
  • Test medium quality, including chloride limits for stainless steel
  • No pressure drop, leaks or visible deformation at welds, joints, flanges and seats
  • Draining, drying and preservation after the test
  • Hydrotest report and pressure chart signed off at the test by vendor QC and the inspector, with gauge serial numbers, test pressure, hold time and result filled in; an unsigned or blank report is not accepted

Test pressure vs actual pressure

The test pressure is the value the test must reach, set by the code, datasheet or approved procedure: for example 1.3 times MAWP corrected for temperature under ASME VIII Div. 1, or 1.5 times the rating for a valve shell test to API 598. The actual pressure is what the calibrated gauges and chart recorder really show during the hold. The test is only valid if the actual pressure stays at or above the required value for the full hold time, without exceeding the upper limit the code or procedure allows.

  • Actual pressure never below the required test pressure; a test held slightly under is repeated
  • Over-pressure within the allowed band, so the part is not overstressed
  • Point of measurement known: ASME VIII defines test pressure at the top of the vessel, so a bottom gauge reads higher by the static head
  • Units consistent: psig vs psia, bar(g) vs bar(a)
  • Gauge range about 1.5 to 4 times the test pressure, calibration certificates valid
  • Report shows both required and actual pressure, hold time, gauge serial numbers, result and signatures

On a performance test, "test vs specified pressure" compares the inlet or discharge pressure on the test stand with the datasheet case. A difference is not automatically a failure, because results are converted to specified conditions, but it must stay within the procedure or ASME PTC 10 similarity limits and be explained by the vendor.

ASME VIII · ASME B31.3 · API 598 · API 6D · API 610

Rotating equipment

Shaft and rotor inspection

The shaft is the rotating element that carries the impeller and runs through the seals and bearings. In high-speed integrally geared pumps and compressors there are two: the low-speed input shaft from the motor and the high-speed gearbox shaft that drives the impeller, often at 10,000 to 25,000 rpm. A small error in material, fit, runout or balance shows up later as vibration, seal leakage or bearing failure, so when "shaft" appears as an ITP line we verify the part itself and its records.

What we check on the shaft

  • Material certificate for the bar or forging, grade per datasheet (for example 17-4PH, 4140 or duplex), heat number traceable to the shaft
  • Dimensional report: impeller fit, seal sleeve and bearing journal diameters, keyway and threads against drawing tolerances
  • Runout and straightness (TIR) on V-blocks or in the lathe against API 610 or the vendor limit
  • Surface finish and hardness at seal and bearing areas

Records and assembly

  • NDT on the finished shaft (PT or MT) and UT of the bar stock where specified, reports reviewed
  • Rotor balance report for the shaft and impeller assembly to API 610 / API 617 or ISO 1940 grade
  • Assembly checks: axial float, end play, coupling fit and final visual for damage
  • During performance and mechanical running tests: housing and shaft vibration against acceptance limits

API 610 · API 617 · ISO 1940 / ISO 21940

Rotating equipment

Seal housing and seal connections

The seal housing, also called the seal chamber, seal housing assembly or, on older drawings, stuffing box, is the pressure-containing part between the pump casing and the bearing housing or gearbox that holds the mechanical seals around the shaft. The impeller is on one side, the bearings on the other, and the seals inside stop process fluid leaking along the shaft. It houses a single, dual or tandem seal with buffer or barrier fluid per the API 682 seal plan on the datasheet, carries the flush, vent, drain, quench and barrier connections, locates the throat bushing and seal sleeve, and forms part of the pressure boundary with its own design pressure and hydrotest.

What we check on the seal housing

  • MTR for the casting or forging (often stainless or duplex), heat number traceable to the part
  • NDT reports: PT on machined sealing surfaces, RT or UT on the casting where specified
  • Hydrotest with the casing at 1.5 times MAWP, hold time recorded, no leaks
  • Dimensions: seal cavity bore, concentricity to the shaft, face perpendicularity and finish of gasket and seal seating faces
  • Seal installation: correct seal part numbers and setting dimensions, faces undamaged
  • During the performance test: seal leakage, flush and barrier pressures, seal housing temperature

Lettered seal connections (Port A, Port B …)

  • Each customer connection is identified by a letter on the general arrangement drawing, with a legend giving its size, thread and function: flush in or out, buffer or barrier in or out, vent, drain, quench, oil or cooling water
  • Letters differ between pump models and seal plans, so they are read from the drawing for that unit
  • Size and thread (for example 1/2" NPT), location and orientation against the legend, so prefabricated seal piping fits
  • Port open and clean, with no chips or casting defects
  • Connected per the seal plan drawing (Plan 11, 21, 53 …), no leak at hydrotest or during the run
  • Correct plug or fitting installed and tagged for shipment

API 682 · API 610 · general arrangement drawing connection legend

Material verification

PMI witnessing (Positive Material Identification)

PMI confirms on the actual hardware that each pressure part is made of the alloy the drawing and MTR say it is. A handheld XRF or OES analyser reads the chemical composition directly on the part, without damaging it, so a carbon steel bolt in a stainless flange, a 316 fitting where 316L or duplex was specified, or a mixed-up heat is caught before it reaches the plant. Mix-ups like these cause corrosion and cracking failures in service that the paperwork alone cannot reveal.

Why the buyer needs it witnessed

  • MTRs certify a heat, not the individual piece that ended up in your equipment
  • Alloy mix-ups are invisible: the parts look identical and pass hydrotest
  • Clients and codes often require 100% PMI on alloy pressure parts and welds
  • A signed PMI record closes the traceability chain from mill to finished item

What we verify

  • Approved PMI procedure, sampling extent and acceptance ranges per element
  • Analyser type (XRF or OES), calibration and check against a certified standard
  • Surface preparation and readings on every required part, weld and fastener
  • Results versus the specified grade and the MTR heat number; PMI marking applied
  • PMI report signed; any wrong-material part quarantined with an NCR

API RP 578 · ASTM E1476 · client PMI specifications

NDT records

RT review (radiographic testing)

Radiographic testing (RT) uses X-rays or gamma rays (Ir-192, Co-60) to image the inside of a weld or casting on film or a digital detector (CR / DR), showing porosity, slag, lack of fusion, incomplete penetration and cracks. Codes such as ASME VIII, B31.3 and API 650 set how much RT a joint needs, from spot to 100%; castings are judged against ASTM E446 / E186 reference radiographs. In an RT review the inspector checks the vendor's radiographs and RT records rather than attending the exposures, usually as a review (R) point in the ITP or as part of the final dossier review.

Why the buyer needs it reviewed

  • RT is a volumetric method: it finds internal defects that VT, PT and MT cannot see
  • Missing shots, unreadable film or an unrepaired reject is a common dossier finding
  • Coverage shortfalls are hard to fix once the equipment is coated and shipped
  • The accepted RT package is part of the code record for the equipment

What we check

  • Every joint required by the ITP and weld map is shot, at the required percentage
  • Film or image quality: density, IQI sensitivity, location markers, no artifacts
  • Technique per the approved procedure; source and exposure recorded
  • Indications called out and dispositioned by a certified Level II / III interpreter (SNT-TC-1A or ISO 9712)
  • Weld, welder and WPS traceability; rejects repaired, re-shot and the extra code-required shots taken

IQI compliance and subcontracted NDT reports

Every film is judged on two separate criteria. IQI compliance means the image quality indicator placed on the part, a wire set or a hole-type penetrameter, shows the required wire or hole on the film, proving the technique reached the sensitivity the code demands. Film density means the darkness of the film is within the ASME V range. A report can show full IQI compliance and still be rejected for density, and the reverse, so we read both columns of the RT report for every exposure rather than only the accept / reject result. Many pump, compressor and vessel shops have no radiography vault of their own and subcontract RT, and often UT, to a local NDT laboratory. The lab's report then arrives through the vendor's quality department. We check that it names the lab's technician and certification level, references the approved procedure and the vendor's weld or casting map, and carries the vendor QC review and acceptance before it enters the dossier. A re-shoot or a deviation on a subcontracted report is the lab's to perform and the vendor's to own; it does not change who is responsible for the equipment.

ASME V · ASME VIII · ASME B31.3 · API 650 · ASTM E446 / E186

NDT records & performance tests

"Density issue": film density or fluid density

A "density issue" on an inspection punch list can mean two unrelated things, and the inspector has to establish which one before it is dispositioned. Next to an RT review it almost always means radiographic film density. In a pump or compressor performance test discussion it means the density of the test fluid versus the fluid the machine is specified for. Occasionally a vendor also uses the word for low density in a casting, meaning porosity or shrinkage seen on a radiograph, which is a material defect to be repaired or rejected rather than a film or test correction problem.

Radiographic film density

Film density is how dark the developed radiograph is, measured with a calibrated densitometer. ASME Section V requires roughly 1.8 to 4.0 in the area of interest for X-ray and 2.0 to 4.0 for gamma sources. A film outside that range is too light or too dark to show defects reliably and is invalid even if nothing is visible on it. Density and IQI sensitivity are separate acceptance criteria: a report can show full IQI compliance (the required wire or hole of the image quality indicator is visible) and still fail on density, and the film is only acceptable when both pass.

  • Density readings on the RT report checked against the code range for every exposure
  • Out-of-range films re-shot and the new films reviewed, or a documented disposition obtained
  • Densitometer calibration and step-wedge comparator record on file
  • Finding raised as a punch item or NCR; the RT package is not accepted with invalid films

Test fluid density on a performance test

Pumps and compressors are shop-tested on water, air or nitrogen while the service fluid is a hydrocarbon, brine or process gas with a different density. Head in metres and polytropic head are independent of density, but differential pressure, absorbed power, flow meter readings and NPSH or surge margins are not, so the test results must be corrected to the specified fluid before they are compared with the acceptance curve.

  • Data sheet density and test procedure density agree; acceptance curve built for the right fluid
  • Measured power corrected for specific gravity so motor or driver sizing is judged correctly
  • Test fluid temperature logged and its density change applied to the correction
  • Flow meter calibrated for the test medium, not the service fluid
  • Vapour pressure and density of the service fluid checked for the NPSH or surge margin

ASME V Article 2 · API 610 · API 617 · ASME PTC 10 · HI 14.6

Shop records

Work order and traveler review

The vendor's work order is the shop's own job paperwork for building or processing a specific item, also called a traveler, router, job card, shop or production order. It identifies the unit (work order and customer PO numbers, tag and serial number, drawing and revision, quantity), lists the routing of operations from material issue through machining, welding, heat treatment, NDT, assembly, hydrotest, performance test, painting and final inspection with a sign-off and date at each step, and records the heat numbers issued to the job, the hold points and any deviations, concessions or rework. In a repair shop the work order may instead define the repair scope.

Why we ask for it

  • Confirms we are inspecting the right unit: nameplate serial number matches the paperwork
  • Shows every step was done in order, with nothing skipped, especially heat treatment or NDT before a test
  • Shows the shop did not proceed past a hold point without notifying the inspector
  • Starts the traceability chain from the assembly back through subcomponents to the raw material

What we check

  • Work order ties to the PO, tag, serial number and current drawing revision
  • Routing sequence and sign-offs against the approved ITP
  • Heat and lot numbers on the traveler match the MTRs and part markings
  • Customer and third-party hold points placed and released correctly
  • Deviations, concessions and rework closed with referenced NCR numbers

Vendor QMS (ISO 9001 / API Q1) · approved ITP · purchase order

Materials & documents

MTR / MTC review and material traceability

On request we take over all Material Test Report (MTR, also called Mill Test Certificate) work for an order, either as part of a shop inspection or as a stand-alone document review. Every pressure-retaining part is traced from its heat number back to a certificate that shows the right specification, grade and results within limits.

  • Heat number match between hardware markings and MTRs
  • Specification and grade check against the PO, Material Requisition (MR) and datasheets (e.g. ASTM A106 Gr. B, A516 Gr. 70, A182 F316L)
  • Chemistry and mechanical values (yield, tensile, elongation, hardness, Charpy) against spec limits
  • Heat treatment condition and supplementary tests: hydrotest, NDT, grain size, PMI
  • EN 10204 3.1 / 3.2 certificate type versus the PO requirement
  • Witnessing of mill or forge tests for 3.2 certification
  • Material traceability matrix for the dossier (MRB)
  • NCR for missing, mismatched or out-of-spec certificates, followed to closure

MTR endorsement

When the scope calls for it, we endorse the MTRs: each accepted page is stamped with the agency or client inspection stamp, signed and dated, and often cross-referenced to the inspection report number. The endorsed certificates go into the final data book as evidence that an independent inspector verified the material certification. Before endorsing we confirm specification and grade against the drawing, PO and requisition, chemistry and mechanical values within spec limits, heat number traceability to the marked part, the EN 10204 certificate level and any supplementary tests, and we look for red flags such as missing heat numbers, altered values, unsigned photocopies or certificates dated after the material was used. A certificate with a deviation is never endorsed; it is raised as a non-conformance instead.

Endorsement carries responsibility for document acceptance, so it is agreed in the assignment. On a witness without endorsement scope we observe and report, and the vendor's quality department and the client's engineers keep responsibility for accepting the documents.

EN 10204 · ASTM / ASME SA material specs · NACE MR0175 / ISO 15156

Release for shipment

Final inspection and Inspection Release Note

The final inspection, also called final visual or pre-shipment inspection, is the last check at the vendor's shop after all manufacturing and testing are complete and before the equipment is packed and shipped. On the ITP it is normally a hold point: nothing ships until the inspector signs it. It is the buyer's last chance to find damage, missing items, wrong orientation or poor preservation while the equipment is still at the vendor and corrections cost hours instead of weeks on site. When it is accepted we issue the Inspection Release Note (IRN), also called release for shipment, which the client uses to approve shipment and payment.

On the hardware

  • Completeness: every item and quantity on the PO and packing list, including spares, special tools and loose-shipped parts
  • Identification: nameplate data, tag and serial numbers against the datasheet, PO and work order
  • Visual and dimensional: no damage after testing, overall dimensions, nozzle orientation and flange ratings against the GA drawing
  • Coating: paint system and colour, dry film thickness, no runs, holidays or bare spots
  • Cleanliness and preservation: drained and dried after testing, internals clean, openings plugged or blinded, desiccant or nitrogen purge, preservation tags
  • Marking and packing: shipping marks, crate condition, lifting points, shock and tilt indicators, export packing per specification

On the documents

  • Every earlier ITP hold, witness and review point signed off
  • Test reports, including hydrotest and performance test, signed with values filled in
  • NCRs and punch items closed or formally accepted by the client
  • Final document review: MTRs, NDT, PMI, calibration certificates and the dossier (MRB) index complete enough to release
  • Certificates of conformity, Ex / IECEx and nameplate certificates where applicable
  • Inspection Release Note issued, or the open items listed so the client can decide

Example: pre-shipment final inspection of lightning protection materials at LEC · Deliverable: Inspection Release Note

Reporting

Flash report and inspection report

A flash report, also called a quick or daily report, is the short preliminary report sent to the client or agency right after each visit, before the formal inspection report. Its purpose is speed: the client needs to know the same day whether a hold point was released so that shipping, scheduling or payment to the vendor can go ahead. We send it before leaving the vendor's site or at the latest the same evening, using the client's or agency's template when one is provided. The full inspection report, with test data, photos and the signed test records, follows within 24 hours of the last activity.

What the flash report contains

  • Job, PO, vendor, location, date and hours on site
  • What was inspected or witnessed, with the ITP line items covered
  • One-line result per item: accepted, rejected or on hold
  • Non-conformances, open punch items and concerns the client should know about immediately
  • Next planned visit or notification
  • Key photos

Same day: flash report · Within 24 hours: full inspection report

Vendor shops and equipment we have inspected

A cross-section of manufacturers where we have witnessed FATs, performed in-process surveillance or reviewed final dossiers.

Compressors & turboexpanders

Performance and mechanical running tests, string tests, dry gas seal and lube oil systems, bare-shaft and bare-frame inspections.

Vendors: Siemens Energy (Dresser-Rand), MAN Energy Solutions, Baker Hughes (Nuovo Pignone), Elliott Group, Atlas Copco Gas & Process, Sundyne, Burckhardt Compression, Ariel, Ingersoll Rand, Howden, FS-Elliott, Rotoflow, Chart (L.A. Turbine), Aerzen

Pumps

Performance and NPSH, mechanical run and vibration, hydrotest, API 682 seal plans, fire-water packages, post-overhaul tests.

Vendors: Flowserve, Sulzer, Ruhrpumpen, ClydeUnion (SPX FLOW), ITT Goulds, KSB, Sundyne (Sunflo), Grundfos, Ebara, Gorman-Rupp, Blackmer, Busch, NASH

Flow, density & instrumentation

Coriolis, density, viscosity, wet gas and multiphase meters, transmitters, fire and gas detection.

Vendors: Emerson Micro Motion, Emerson Roxar, Rosemount, Anton Paar, KROHNE, Endress+Hauser, TechnipFMC, Baker Hughes Panametrics, Sensia, Cameron NUFLO, Yokogawa, Pietro Fiorentini, Honeywell Analytics, Det-Tronics, Dräger

Valves & fittings

Shell and seat tests, actuator and positioner function, material traceability, marking and packing.

Vendors: Emerson Fisher, Cameron, Velan, Flowserve, Powell, Anix, Swagelok, SPX Copes-Vulcan

Heat exchangers, vessels & boilers

Hydrotests, weld NDT, tube-to-tubesheet joints, dimensional surveys, ASME data reports.

Vendors: Graham, GEA, Alfa Laval, API Heat Transfer, Tranter, SWEP, Croll-Reynolds, Schutte & Koerting, Körting, Babcock & Wilcox, GE Power, Cleaver-Brooks, Rentech, Superior Boiler, Victory Energy, CST Industries

Electrical, turbines & packages

Transformer and switchgear FATs, motors and generators, steam and gas turbines, cranes, cooling towers.

Vendors: Siemens Energy, Siemens, Hitachi Energy, Eaton, Baldor, SEW-Eurodrive, Caterpillar, GE Power, Konecranes, SPX Cooling, Legrand

Standards and credentials

Certifications
  • ASNT NDT Level II (SNT-TC-1A): PT, MT, UT
  • 10+ years vendor and third-party inspection
Rotating equipment
  • API 617, 618, 672 compressors
  • API 610, 682 pumps
  • ISO 10816 vibration
Pressure equipment & welding
  • ASME VIII, IX, V
  • API 598, API 6D, ASME B16.34
  • TEMA, HEI
Instrumentation & electrical
  • IEC 61508, ATEX / IECEx
  • AGA 9, ISO 5167
  • IEC 60076, IEC 62271
Vlad Kost, third-party inspector, Coriolis Inspection Services LLC
Your inspector

Vlad Kost

Senior rotating-equipment and mechanical third-party inspector, founder of Coriolis Inspection Services LLC.

Based in
Boulder, Colorado
Experience
10+ years vendor and third-party inspection
NDT
ASNT Level II PT, MT, UT
Email
vlad@coriolis-calibration.com

About

Coriolis Inspection Services LLC started with independent FAT witnessing of Coriolis flow meters at the Emerson Micro Motion plant in Boulder, which gave the company its name. The scope today is the full range of vendor inspection that oil and gas, petrochemical and power projects need: compressors and turbomachinery, pumps and drivers, flow metering and instrumentation, valves, heat exchangers and vessels, and electrical equipment.

Before founding the company, Vlad spent more than ten years as a vendor and third-party inspector on projects worldwide, with a specialisation in compressors and turbomachinery to API 617, 618 and 672: performance and mechanical running tests, aerodynamic tests at multiple speeds, string tests, dry gas seal and lube oil system checks, overspeed and rotor balance verification, and internal and bearing dismantling inspections. He is ASNT NDT Level II in PT, MT and UT and experienced in ITP and drawing review, welding and NDT coordination, MTC and PMI verification, NCR handling and final dossier review.

Being based in Colorado puts him within a short drive of several vendor shops that regularly host FATs for international projects, and available at short notice when test dates move.

How an assignment runs

  1. Send the scope

    NOI or test dates, ITP, PO and datasheets, test procedures, shop address. A reply with availability comes within 24 hours.

  2. Preparation

    We review the ITP, procedures and acceptance criteria, and prepare the checklists for each hold and witness point. When the vendor asks for the SQR who will be on site, we send name, company, contacts, dates and any ID or safety induction forms needed for site access.

  3. On the test floor

    We attend each point, verify instruments and calibrations, record readings and photos, and sign the vendor's protocols.

  4. Reporting

    Flash report the same day; full report with test data, photos, NCRs and punch list within 24 hours.

  5. Release

    NCR follow-up to closure, final dossier review and the Inspection Release Note for shipment.

Industries served

Projects where test results, material integrity and documentation decide whether equipment can be accepted and shipped.

  • Oil & gas: upstream, midstream, offshore and downstream
  • LNG, gas processing and vapour recovery
  • Refining, petrochemical and chemical plants
  • Hydrogen, CO₂ and alternative energy systems
  • Power generation and utilities
  • Pipelines and custody transfer metering
  • Pharmaceutical, food and high-purity processes
  • EPC contractors and third-party inspection agencies

Frequently asked questions

Looking for a specific abbreviation such as ITP, NOI, MTR, PMI or RTP? See the glossary of inspection terms.

What does a third-party witness inspector do?

A witness inspector attends the tests and inspections listed in the Inspection and Test Plan (ITP) at the vendor's shop on behalf of the buyer. The inspector verifies that each test is run per the approved procedure and acceptance criteria, reviews certificates and records, raises non-conformances, and issues an inspection report and release note.

Who do you work for?

Owners, operators, EPC contractors and third-party inspection agencies that need a qualified inspector at a vendor shop. We never work for the vendor whose equipment is being inspected.

Can you act as our SQR at the vendor's shop?

Yes. SQR stands for Supplier Quality Representative, sometimes Source Quality Representative: the person who attends the vendor's shop on the buyer's behalf to witness tests, release hold points and check quality. We act as the SQR for owners and EPC contractors directly, or on behalf of an inspection agency. When the vendor or coordinator asks for the SQR who will be on site, we provide the name, company, phone and email, attendance dates and arrival time, and any passport or ID copy, visitor or safety induction forms the shop needs for gate access, so badges are ready and the named SQR can sign off the hold points.

What information do you need to schedule an inspection?

The Notification of Inspection (NOI) or test dates, the ITP with hold and witness points, the purchase order and datasheets, applicable test procedures and the shop address and contact. If some of these are missing we can still attend and will note the gaps in the report.

How fast do you deliver reports?

A flash report is sent the same day for each attended hold or witness point. The full inspection report with photos, test data and any non-conformance reports follows within 24 hours of the last activity.

What is a final inspection?

The final inspection, also called pre-shipment inspection, is the last hold point at the vendor's shop after all manufacturing and testing are complete and before packing. We check completeness against the PO and packing list, nameplates, tag and serial numbers, visual condition, dimensions and nozzle orientation against the GA drawing, coating, cleanliness and preservation, marking and export packing, and confirm that all earlier ITP points are signed, test reports are complete and NCRs are closed. When it is accepted we issue the Inspection Release Note (IRN), which the client uses to approve shipment and payment.

What is a flash report?

A flash report is the short preliminary report sent to the client or agency right after an inspection visit, before the formal report. It lists the job, PO, vendor, date and hours on site, the ITP items inspected or witnessed with a one-line result for each (accepted, rejected or on hold), any non-conformances or concerns, the next planned visit and key photos. We send it the same day, so the client knows at once whether a hold point was released; the full inspection report follows within 24 hours.

What do you check on a pump or compressor shaft?

We verify the shaft material certificate and heat number traceability, the dimensional report for impeller fit, seal and bearing journals, runout and straightness against API 610 or vendor limits, surface finish and hardness at seal and bearing areas, NDT reports, the rotor balance report, and assembly checks such as axial float and coupling fit. During performance and mechanical running tests the shaft condition also shows up in the vibration readings we record.

What does an inspector check on a pump seal housing and its ports?

The seal housing holds the mechanical seals around the shaft and is part of the pressure boundary. We review its material certificate and NDT reports, witness the hydrotest, check the seal cavity dimensions and seating faces, and verify the seal installation. Each seal connection is lettered on the general arrangement drawing (Port A, Port B and so on) with a legend giving size, thread and function, such as flush, barrier, vent or drain; we check every port against that legend for size, orientation, cleanliness, connection to the API 682 seal plan, plugging and tagging, and watch for leaks at hydrotest and during the performance test.

What is an FTP in an inspection and test plan?

FTP usually means Factory Test Procedure, sometimes Functional or Final Test Procedure: the vendor's written procedure for a shop test, with scope, references, test setup and instruments, step-by-step method, acceptance criteria and data sheets. It is approved by the client before the FAT and is the document the witness inspector judges the test against. We check that the approved revision is used, that the setup, instruments and every test step follow it, compare the results with its acceptance criteria, record any deviations and make sure the data sheets are completed and signed at the test.

Why are compressors tested on nitrogen or CO2 instead of the process gas?

A hydrocarbon or sour process gas cannot be run safely in a shop test loop, so the performance test is run as an ASME PTC 10 Type 2 test on a substitute gas and converted to the specified conditions. Nitrogen is inert and often matches a real start-up or minimum-speed case; CO2 is heavier and reproduces the head and volume ratio of a heavier process gas at an achievable speed, so multi-stage compressors are often tested on both. We check the test gas analysis, the similitude calculation, each test case and the instrument calibrations, and compare the converted head, flow and power with the API 617 and purchase specification tolerances.

What is an in-process (IP) inspection?

An in-process inspection is a visit during manufacturing, between the pre-inspection or kick-off meeting and the final inspection. We check material identification and heat numbers, fit-up and welding, NDT and PMI as performed, intermediate dimensions, heat treatment records, assembly clearances, balance and seal installation, and coating preparation, so that problems are found while they can still be fixed cheaply, before they are hidden by machining, assembly or paint.

What is an MR (Material Requisition)?

The Material Requisition is the EPC contractor's or owner's technical purchasing document for an item. It defines what is being bought: datasheets, specifications and standards, scope of supply, inspection requirements and the documents the vendor must deliver. The purchase order references the MR number and revision, so when a PO says the item is supplied per MR, the specification, grade and test requirements we inspect against are found in the MR. It is different from the MRB, the Manufacturer's Record Book or final dossier.

Why should a hydrostatic test be witnessed?

The hydrostatic or pressure test is the proof that pressure equipment is strong and leak-tight, and it is a mandatory hold point in almost every ITP. Once the equipment is coated, assembled or installed, defects are hard and expensive to find. An independent inspector confirms the approved procedure, test pressure and hold time, checks gauge calibration and test water quality, looks for leaks and pressure drop, and signs the test certificate that goes into the dossier for owner and jurisdiction acceptance.

What is the difference between test pressure and actual pressure?

Test pressure is the required value from the code, datasheet or approved procedure, for example 1.3 times MAWP under ASME VIII Div. 1 or 1.5 times the rating for an API 598 valve shell test. Actual pressure is what the calibrated gauges and recorder show during the hold. We confirm that the actual pressure stays at or above the required value for the whole hold time without exceeding the allowed over-pressure, that it is measured at the right point and in the right units (psig or psia), that gauges are calibrated and correctly ranged, and that both values are recorded on the signed report. On a performance test, a difference between test-stand and datasheet pressure must stay within the procedure or PTC 10 similarity limits.

What does "RTP on hold" mean?

RTP is the Release to Proceed: the go-ahead for the vendor to continue past a hold point or to ship. RTP on hold means that release is withheld until something is resolved, typically an open non-conformance or defect, a client review of test results, missing documents such as calibration certificates or the approved procedure, or a pending NOI revision. While the RTP is on hold we do not sign the step as accepted or issue a release note; we record in the flash and inspection report that the RTP is on hold, the reason, who placed the hold and what is needed to lift it, and we continue to witness and report any activities the client allows. The release is given by the client or agency once the open issue is closed.

Do you make sure test reports are signed off?

Yes. Every test we witness, starting with the hydrostatic test, is signed off on the spot by vendor QC and by us, with the actual values recorded: gauge serial numbers and calibration dates, test pressure, hold time and result for a hydrotest, and the same for PMI, NDT, dimensional, performance and functional tests. Reports and pressure charts are not left blank to be filled in later, and an unsigned or incomplete report is not accepted into the dossier. Signed reports are what the owner, the EPC contractor and the authority having jurisdiction rely on to accept the equipment.

Why is PMI witnessed at the vendor shop?

Positive Material Identification (PMI) checks the actual chemistry of each part with a handheld XRF or OES analyser. Material certificates cover a heat, not the individual piece, and a wrong alloy looks identical and still passes hydrotest. A witnessed PMI confirms that every specified pressure part, weld and fastener is the right grade, matches the MTR, and is recorded in a signed PMI report before shipment.

What does an RT review include?

In an RT (radiographic testing) review we check the vendor's radiographs and RT reports instead of attending the exposures: that every joint required by the ITP was shot at the required coverage, that film or image quality and IQI sensitivity meet the code, that the technique follows the approved procedure, that indications were dispositioned by a certified Level II or III interpreter, and that rejected welds were repaired and re-shot. Film density and IQI sensitivity are checked separately for each exposure, since a film can meet one and fail the other, and reports from a subcontracted NDT laboratory are checked for technician certification, procedure reference and the vendor's own QC acceptance. Gaps are raised as punch items or non-conformances.

What is a density issue on an inspection punch list?

A density issue is one of two unrelated things. Next to an RT review it means radiographic film density: how dark the film is, which ASME Section V keeps between about 1.8 and 4.0 for X-ray and 2.0 and 4.0 for gamma. A film outside that range is invalid even if it shows no defect, so we ask for the re-shot films or a documented disposition and do not accept the RT package until it is closed. In a pump or compressor performance test it means the density of the test fluid, usually water, air or nitrogen, versus the specified service fluid. Head is independent of density but differential pressure, absorbed power, flow readings and NPSH or surge margins are not, so we check that the data sheet and test procedure densities agree, that the measured power is corrected for specific gravity, that test fluid temperature was logged and applied, and that the flow meter was calibrated for the test medium. Occasionally a vendor also uses the word for low density in a casting, meaning porosity or shrinkage on the radiograph, which is a material defect to repair or reject.

Why does the inspector ask for the vendor's work order?

The work order, also called a traveler, router or job card, is the shop's own record for building a specific item: it identifies the unit by PO, tag, serial number and drawing revision, lists every manufacturing step with sign-offs, and records the heat numbers issued to the job, hold points and any deviations or rework. We use it to confirm we are looking at the right unit, that each step was done in the right order with nothing skipped, that no hold point was passed without notice, and to start the traceability chain back to the material certificates.

Do you review MTRs and material certificates?

Yes. On request we handle all Material Test Report (MTR / MTC) work for an order: matching heat numbers on the hardware to the certificates, checking specification, grade, chemistry, mechanical properties and heat treatment against the PO and material specs, confirming EN 10204 3.1 or 3.2 certification, witnessing mill tests for 3.2 certificates, and building the material traceability matrix for the dossier. Missing or mismatched certificates are raised as non-conformances and followed to closure. This can be part of a shop inspection or a stand-alone document review.

What does MTR endorsement mean?

Endorsing an MTR means the inspector stamps, signs and dates the material test report to certify that it was reviewed and accepted: grade and specification match the drawing and PO, chemistry and mechanical values are within limits, the heat number traces to the marked part, and the certificate level and supplementary tests meet the order. Endorsed MTRs go into the final data book. Because endorsement carries responsibility for document acceptance, it is agreed in the scope; a certificate with a deviation is not endorsed but raised as a non-conformance, and on a witness-without-endorsement assignment we observe and report without stamping documents.

Are you qualified in NDT?

Yes. ASNT NDT Level II (SNT-TC-1A) in Liquid Penetrant, Magnetic Particle and Ultrasonic Testing, which allows us to witness, interpret and review NDT and to perform PT, MT and UT checks where the contract permits.

Can you take urgent assignments?

Yes. Short-notice attendance at Colorado shops is often possible the next working day. Call or send the NOI and we will confirm availability the same day.

Need an inspector at a vendor shop?

Send the NOI or test dates and the equipment scope. We confirm availability within 24 hours.

Call now WhatsApp Request inspector